OPTIMISING
OPERATIONS IN INTERIOR DESIGN BUSINESS PROCESS AT PT. BLESSED KREASINDO HOUSE
Fakhrian
Maulana1, Liane Okdinawati2
Master of Business Administration, School of
Business and Management, Institute Bandung Technology
Email: [email protected]1,
[email protected]2
|
Abstract |
|
This study aims to improve and streamline business procedures at PT.
Kreasindo Blessing House . The study's history is thoroughly covered
throughout the paper, emphasising the topic's importance and how it relates
to the business's operations. This study's primary focus is on the problem of
project delays, which has been seriously hurting PT. Rumah Kreasindo Berkah's
finances. It is a fresh topic of inquiry because the efficiency advances of
the interior design industry have yet to be thoroughly studied. Research to
date has yet to address this sector's potential for optimisation. A
combination of observational methods and interviews with upper management
were used in this study. The study includes an analysis of the complete
production flow and internal staff members of PT. Kreasindo Blessing House .
The study produces new business procedures and well-thought-out solutions to
improve productivity and shorten project turnaround times. The results will
provide suggestions for increasing productivity and reducing project
implementation delays. Each organisation applies efficiency measures
differently, and theoretical ideas might not match actual situations. This study
emphasises how crucial it is to modify efficiency tactics to fit the
particular circumstances of each business, providing insightful information
to academics and business professionals. Keywords: Business Process,
DMAIC, Fishbone, Interior Design, Efficiency. |
According to CNBC Indonesia, the demand for interior design has
increased, and the increase began to be seen in the first quarter of 2022. The
increase touched 45% and is expected to increase further. Not only that, the
rise of property development has also contributed to the high demand for
interior design services. This is inseparable from the incessant development of
the property sector, especially in big cities (Hasibuan, 2022).
�� PT Rumah Kreasindo Berkah is an
Interior Consultant company engaged in the creative industry. Established in
2018, PT Rumah Kreasindo Berkah, better known as Rumah Louie Project (RLP), is
engaged in architecture and interior consulting. Carrying the concept of a
"one-stop Interior Design Provider", RLP provides all client needs
from design to build and service for long-term maintenance. In the fierce
competition in the Interior design industry, PT Rumah Kreasindo Berkah has an
excellent increasing trend of project volume from FY2021 until FY2022. The
increase in the number of projects completed by RLP is 115%. However, on the
side of work that has been running, it is often encountered that some projects
experience delays, resulting in increased work time and other costs that arise
from this due to a delay in Q1 and Q2 2023, in Q3 2023 PT. Rumah Kreasindo
Berkah has only achieved 20 projects so far. The CEO of RLP has a target of
completing 45 projects in FY2023. From 2021 to Q3 2023, the number of delays
recorded at PT. Rumah Kreasindo Berkah accounted for 39% of the total 61
projects completed in that period. This is one factor that needs improvement to
increase effectiveness and profit margins.
As a result of an interview with the owneprojectr
of PT Rumah Kreasindo Berkah, delays in a project being completed on time can
result in direct and indirect financial losses. Direct losses can take the form
of potential profits for the company because it cannot add new projects. After
all, the old project still needs to be completed, increasing operational costs.
In addition, indirect losses from the delay of a project will reduce customer
satisfaction and lousy brand image and reduce the possibility of clients using
our services again. By evaluating this matter, it is hoped that PT. Rumah
Kreasindo Berkah can overcome project delays, increase operational
effectiveness, and achieve better profit margins.
According to Creswell (2013), qualitative research
explores and understands the meaning individuals or groups ascribe to a social
human problem, focusing on observations and interviews with high-ranking
officials such as the CEO, Project Manager and Project Supervisor at PT. Rumah
Kreasindo Berkah, this method was adopted to gain direct and in-depth insight
into critical aspects to optimise operational efficiency in the interior design
production process. By combining field observations and in-depth interviews,
this research presents a holistic and in-depth picture of operational
conditions at PT. Kreasindo Blessing House.
1.
Interviews
Adams
(2021) characterises interviews as guided discussions where interviewers raise
issues and probe interviewees to uncover their insights. He states that
interviews involve "directed conversations" (p.77), distinguishing
them from casual dialogue. The main characteristic of an interview is direct
face-to-face contact between the information seeker and the information source.
The chosen interviewees represent crucial perspectives, with the CEO of PT.
Rumah Kreasindo Berkah provides overarching insights, the Project Manager is
the custodian of identified challenges, and the on-site supervisor contributes
invaluable practical considerations.
2.
Observations
According to Abdullah
and Saebani (2014), observation is a data collection technique that involves
directly observing the field regarding the problems discussed in the research.
The observation in this research is passive participant observation: the researcher
observes but is not involved in the activity (Abdullah, 2014). Observations
were carried out to see the production flow by PT. Kreasindo Blessing House.
Researchers went directly to the field accompanied by the project manager to
see the production flow from the start of production to the end of the project
completion. This observation aims to understand better how the process takes
place, identify potential waste, and evaluate operational performance directly.
3.
Secondary data
Sugiyono (2018) states
that secondary data is a source that does not directly provide data to
collectors. Secondary data in this study were obtained from reference books,
research journals, the internet, and historical company performance data. Using
past performance data, a corporation can make decisions based on information
that helps project managers make iterations and continuously improve project
planning and execution.
As Moser and Korstjens (2018) describe, "Data
analysis aims to uncover embedded information and develop interpretations of
personal experiences and social worlds". Several methods can help the
researcher improve the efficiency of the supply chain at PT Rumah Kreasindo
Berkah. In general, the researcher will examine using Six Sigma with one of the
tools, DMAIC, by regularly applying the DMAIC method, PT. Rumah Kreasindo
Berkah can improve efficiency, reduce uncertainty, and increase quality in its
interior design production process.
After
implementing data collection methods, which involved collecting historical
data, observations, and interviews with high-ranking officials at PT. Rumah
Kreasindo Berkah, this chapter will discuss the findings and analysis resulting
from the data collected. These results provide an essential basis for
understanding challenges, opportunities, and recommendations to optimise
operational efficiency in interior design production (Frank et al.,
2019). In this stage, the research adopted a
systematic approach using the DMAIC (Define, Measure, Analyse, Improve,
Control) method to thoroughly analyse the challenges and opportunities faced by
PT. Rumah Kreasindo Berkah in optimising operations in the interior design
production process (Ahmed, 2019).
1 Define Phase
Using DMAIC, the defining stage will help
identify the analysis goals, objectives, and critical parameters that need to
be evaluated (Kaid et al.,
2016). PT. Rumah Kreindo Berkah's problems could
benefit the company and the client more. Based on historical data from PT.
Rumah Kreasindo Berkah can only work on 61% of its projects on time. This data
is taken from historical data for 2021 to Q3 2023, based on the results of
interviews conducted with the project manager, supervisor, and CEO of PT, Rumah
Kreasindo Berkah, several problems reduced the company's profit margin and
potential loss, such as as as as as as as Long Length of Approval, Complex
Production Flow, Scarcity of a supporting item, Measurement error, Installation
Error, Location that is not ready, Limited workforce. These problems are what
cause project delays at PT. Kreasindo Blessing House . This project delay
caused the company to suffer from a potential loss (Parpongpun,
2020). If PT. Rumah Kreasindo Berkah cannot achieve
its target or is only able to achieve 80% of what is targeted. The company will
lose 3.8 Billion IDR from losing 9 potential projects that could be carried out
in 2023. The number is obtained from the average project value multiplied by
the number of projects that cannot be carried out in 2023 (Rosengart et
al., 2023). With the data collected in the define phase,
the researcher knows the problems, which the author will then measure and
analyse in the next phase (Guest, Namey,
& Chen, 2020).
2 Measure Phase
The Measure stage will collect and evaluate
historical data, observations, and interviews to deeply understand the interior
design production process before analysing and measuring the severe PT delays.
Rumah Kreasindo Berkah, the researcher, needs to know which projects have the
most significant delays. This information was obtained from an analysis of
historical data collected by the author.
Table
1. Project Delay
Percentage
|
Project Type |
Number of Projects |
Delay (in days) |
Percentage |
|
Full
House |
15 |
7 |
46% |
|
Half
House |
24 |
11 |
45% |
|
2
Rooms or less |
16 |
6 |
37% |
|
Commercial 3D
Design |
4 2 |
0 0 |
0% 0% |
Based on Table 1 It is evident that projects
characterised by a high level of difficulty and complexity often encounter
delays. Specifically, 46% of full-house projects at PT. Rumah Kreasindo Berkah
experienced delays from 2021 to Q3 2023. Full-house projects typically involve
a substantial time investment and carry significant financial value. To
comprehensively assess the urgency of issues at PT. Rumah Kreasindo Berkah,
several measurable data points can be examined. Firstly, analysing the average
value of projects undertaken by the company provides insight into these
endeavours' overall scale and financial magnitude. Second, evaluating trends
based on project numbers can reveal patterns or fluctuations in the volume of
projects undertaken by PT. Kreasindo Blessing House . Lastly, examining the
average delay in days that projects experience is crucial for understanding the
timeliness and efficiency of the production process.
Figure
1 Growth Trend
From the figure 1 PT. Rumah Kreasindo Berkah is
currently experiencing a growth trend in the number of projects, with the
number of projects for 2022 being the highest. Notably, there has been a shift
in the project composition, with a higher prevalence of small projects compared
to previous years when there were more full-house projects. Figure 4
illustrates this trend, highlighting a lower average value in 2022, primarily
attributed to the distribution of smaller projects. This is different from
2021, which has fewer numbers but a more excellent average value because there
are more full-house projects that year.
3 Analyse Phase
The analysis phase became the primary focus for
understanding the critical aspects that influence operational efficiency in
PT's interior design production process. Kreasindo Blessing House . (Compagnucci,
Corradini, Fornari, Re, & Tiezzi, 2021)Discusses investigative analysis to pinpoint
causes of declining process efficiency by mapping current states, establishing
metrics, verifying relationship significance, and narrowing vital factors. By
following this methodical process, the study will investigate insights obtained
through observational assessments and interviews, employ the DMAIC framework
for data analysis, and lead readers to a more profound understanding of the
company's difficulties and the potential avenues for improvement that can be discerned.
Initially, the researcher performs an analysis using Business Process Modeling.
4 Business Process
Apart
from knowing which projects are experiencing significant delays, the author
also needs to analyse the business processes at PT. Kreasindo Blessing House.
Knowing which phases/parts often have the most significant potential for delays
is necessary. The business processes carried out at PT. Kreasindo Blessing
House. The business process starts with a customer request and ends with
quality control and handover. Here is the actual flow of business processes
that occurs in PT. Kreasindo Blessing House.
Figure 2 Swimlane Preparation Phase
Apart
from knowing which projects are experiencing significant delays, the author
also needs to analyse the business processes at PT. Kreasindo Blessing House.
Knowing which phases/parts often have the most significant potential for delays
is necessary. The business processes carried out at PT. Kreasindo Blessing
House. The business process starts with a customer request and ends with
quality control and handover. Here is the actual flow of business processes
that occurs in PT. Kreasindo Blessing House.
Figure
4 shows the production flow in the first phase of PT. Rumah Kreasindo Berkah's
entire business process and assigned responsibilities are depicted. Several
phases in the figure have been identified, with potential delays, as
highlighted by insights from interviews with project managers and supervisors.
In the initial phase, three approvals are required to proceed with the process.
According to the results of interviews conducted with supervisors, one of the
frequent causes of delays is the time required for approval. The following
process is production preparation. The production preparation process will
begin after the CEO approves the 3D design in this phase. The process will be
depicted in the swimlane diagram below.
�
Figure
3 Swimlane Diagram Production Preparation
In
the production preparation phase, potential delays may occur when clients
request revisions, requiring additional approval. Moreover, observations at PT.
Rumah Kreasindo Berkah's office reveals common delays in data collection after
kick-off meetings. The workshop, design, and finishing teams are tasked with
compiling a list of project items within a 3-day deadline. However, field
realities often include delays in collecting this list, hindering raw material
procurement and potentially delaying the start of production. The
subsequent phase is the production process conducted in the workshop area. Two
teams, the wood workshop team and the finishing workshop team, jointly operate
in the same workshop space to minimise the time required for goods movement.
Figure
4 Swimlane Production
The
subsequent phase is the project installation process, as highlighted in
interviews with the CEO and Project Manager, frequently plagued by prolonged
delays. These delays are particularly noticeable to clients at the project
location, potentially leading to declining customer satisfaction. The
installation process is elucidated in the swimlane
diagram below.
Figure
5 Swimlane Installation Phase
During
the installation phase, numerous areas pose a potential for errors leading to
delays. For example, errors during on-site goods installation may necessitate
on-site repairs, extending work time due to measurement inaccuracies. Colour
confirmation can also be problematic, potentially causing delays if client
approval is delayed. Interviews with on-site supervisors reveal that problem
resolution at the location often experiences prolonged delays, especially for
significant issues that may require approval from the CEO or the client. Next
is the last stage of the business process that occurs in the PT. Rumah
Kreasindo Berkah, the finishing stage, is shown in Figure 6.
Figure
6 Swimlane Finishing Phase
In
the last phase, a step could still be delayed. If a defect does not pass the
quality check, a revision will take time. Of all the phases that have passed,
many potential problems could cause delays, and these need to be corrected
immediately. The following is a summary of problems in PT's business processes.
Kreasindo House of Blessings:
Table
2 Project Delay Percentage
|
Phase |
Potential
Problems |
|
Preparation |
There
are too many approvals and long-time responses. |
|
Production Preparation |
The
client asks for revisions many times |
|
Production Preparation |
The
production team and the finishing team were late in providing reports and a
list of project requirements due to too many parallel projects |
|
Production Preparation |
budget
approval takes a long time because the CEO is busy |
|
Production Preparation |
Unavailability
of goods and scarcity of raw materials |
|
Production |
Unavailability
of production-supporting goods |
|
Production |
The
colour selection is still changing |
|
Installation |
Measurement
errors requiring changes in location |
|
Installation |
Revision if an error
occurs, which requires a long process and approval |
|
Finishing |
Found a defect during QC,
so a revision had to be carried out |
|
Finishing |
Complementary goods are
unavailable, so the project cannot be handed over. |
5 Ishikawa Diagram
Figure
7 Fishbone Analysis
The second tool used in this research is the
Ishikawa Diagram, also known as the Fishbone Diagram. It gets its name from its
form, which is the shape of the skeleton of a fish. It was devised by Professor
Kaoru Ishikawa, who pioneered the quality management process in the Kawasaki
Shipyards in the 1960s (Septiawan &
Bekti, 2016). In this chapter, Fishbone analysis becomes an
exploratory focus to outline the main factors contributing to operational
efficiency in PT's interior design production process. Kreasindo Blessing House
. This chapter will analyze the causes of the delay in more depth, which will
later become material for improvising plans.
After knowing the most crucial problems, the
company can sort them from the most influential to the least influential. Next,
the company needs to find the best solution that can be applied appropriately.
The author can find the PT from the problem analysis process using business
process modelling to identify the problem area and fishbone analysis to
categorize and validate the emerging problem by understanding the root cause of
project delays at PT. Rumah Kreasindo Berkah, such as time-consuming approvals,
lengthy bureaucracy, unclear communication flows, and so on, the company can
find out what causes the decreasing profit margins, significant potential risks
of loss, unpredictable additional costs, and low service quality to clients in
terms of timeline. The company needs to improve it to avoid more significant
effects; there are several ways to fix it, such as designing new business
processes based on the analysis carried out in the business process. Pay
attention to reducing unnecessary steps, identifying areas that need
automation, and restructuring workflows to be more efficient.
6 Improve Phase
Based on the analysis findings, potential
solutions have been identified to address the identified problems effectively.
The researcher will employ a solution selection matrix based on fishbone
analysis, offering solutions for each problem and aiming for the new business
process based on the proposed solution. (Mundra &
Mishra, 2023)describes the Solution Selection Matrix as an
analytical tool that enables teams to propose and rank solutions for root
causes, considering risk-benefit tradeoffs, resource utilization, and solution
maturity criteria.
The Solution Selection Matrix results indicate
several implementable solutions to improve the flow of business processes at
PT. Kreasindo Blessing House . The project manager's input, collected through a
Google form, was crucial in prioritizing these solutions based on the existing
situation. The selection process involves evaluating each solution's
effectiveness, feasibility, and cost-benefit rating. Here is a summary of some
recommended solutions to address project delays.
Table
3. Purposed Solution
|
No |
Solutions |
|
1 |
Adopt
cloud-based data platforms that offer centralized storage and easy
accessibility |
|
|
2 |
Implement a quality assurance process for all
products before the installation phase. This involves checking for defects,
damages, or any discrepancies that may hinder the installation process |
|
|
3 |
Ensure that product specifications and
location measurements are detailed and accurate in the project documentation |
|
|
4 |
Determine one project leader as the person
whom the client can contact. |
|
|
5 |
Implement a system to monitor the availability
of critical products. |
|
|
6 |
Ensure that the client's specifications,
criteria, and expectations regarding the design are precise and agreed upon
before the project begins |
|
|
7 |
Conduct a thorough analysis of existing
bureaucratic processes |
|
|
8 |
Save a buffer stock of essential products
(products that are frequently used) |
|
|
9 |
Plan the project schedule carefully and avoid
stacking too many projects at once. |
|
|
10 |
Conduct intensive and proactive coordination
with the project owner or party responsible for site readiness. |
|
A
new business process will be devised to enhance the business process flow in
alignment with the previous analysis. Initiating with a preparatory phase, this
process begins when the client contacts the company and concludes with the 3D
design stage. To accelerate the process, several changes involve the
consolidation of multiple processes. The CEO approval process, initially
occurring twice, is now streamlined to once, coinciding with the completion of
the 3D design and the Project Manager bundling the design. Accompanying this,
adjustments ensure that the design and finance teams adhere to predefined
guidelines for creating budget plan estimates and mood board styles by PT.
Rumah Kreasindo Berkah standards.
Figure 8 Purpose Preparation Process
In
Figure 8, the swimlane diagram, activities
highlighted in yellow require adjustments to existing business processes. To
minimize reliance on CEO confirmation, the finance and design divisions must
adhere to predefined standards, eliminating the need for frequent approvals. In
the proposed process, timeline creation occurs at the design's initiation,
facilitating the parallelization of tasks and enhancing project transparency
for clients.
To
mitigate delays caused by excessive approvals in the production and
installation phases, all design specifications, including colour, size,
accessories, etc., are approved at the project's outset. Creating a design
bundle ensures comprehensive visualization and specification representation,
including the client's contract signature, indicating agreement with the
specified project details. Figure 8 illustrates the proposed new process
highlighted in green, enabling clients to articulate changes to design,
colours, and accessories while the project is ongoing. Given that production
and installation are in progress, modifications to specifications at this stage
may result in additional costs due to completed goods purchases.
The
production preparation process will be significantly streamlined in the
subsequent phase as all client approvals were obtained at the project's
outcome. Consequently, all determinations of the list of requirements align
with the specifications outlined in the design bundle. Figure 8 illustrates the
simplified flow of the production preparation process. However, before the
procurement team completes all purchases, a final check by the CEO is still
necessary to ensure there are no excessive acquisitions.
Figure 9 Purposed Production Preparation Proces
After
all purchases are completed, raw materials will be directly sent to the
workshop by the vendor, while supporting goods undergo initial inspection in
the warehouse for completeness and quality. Additionally, the design, workshop,
and finishing teams are assigned the task of compiling a project�s required
goods list within a 3-day timeframe. With the conclusion of the production
preparation phase, the business process seamlessly transitions to the
production phase.
Figure 10 Purposed Production Process
In
the production process, there are no changes to the workflow as it is effective
with minimal delays. The early approval of material, colour, and accessory
specifications allows for a smooth and obstacle-free execution (Wilson et al.,
2021). This positively impacts the workshop's
efficiency, enabling increased monthly goods production. Attention should be
given to consistently monitoring the availability of essential goods to prevent
material shortages. Moving to the installation process at the project site,
observations and interviews at PT. Rumah Kreasindo Berkah indicates that this
phase frequently encounters delays.
Figure 11 Purposed Installation Process
In
Figure 11, the following flow for the installation process will be explained.
The project manager delegates his responsibilities to the supervisor. However,
he has to control the project periodically to ensure everything follows the
guidelines. Following the completion of installation, the project manager must
conduct a quality check with the supervisor before proceeding to a quality
check with the client and CEO (Meredith et al.,
2017). Once the quality check is finalized, the
process seamlessly transitions to the finishing phase (Serban &
Marinescu, 2013). In this final phase, minimal process changes
are anticipated as the preceding quality control phase aims to minimize
revisions. This ensures a smooth execution, contributing to the project's
timely completion.
7 Control Phase
In this control phase, the main objective is to
monitor, measure, and validate the implementation of the solution to ensure
that the proposed changes can be adopted successfully in PT. Rumah Kreasindo
Berkah (Rifqi, Zamma,
Souda, & Hansali, 2021). Therefore, there is a need to adjust KPIs and
SOPs to support new business processes. This is to maintain the implementation
plan, keep it on track, and fix the problems in the company. With this
solution, companies can avoid delays, such as reduced project margins, high
potential losses, and additional costs arising from these delays (Alsharef et al.,
2021).
From the analysis results, it can be concluded
that the interior design production process at PT. Rumah Kreasindo Berkah faces
significant challenges. These challenges, including project delays, declining
profit margins, and potential lost opportunities, contribute to reduced
profitability and competitiveness. By gaining a deeper understanding of these
issues, PT. Rumah Kreasindo Berkah can implement targeted solutions to improve
operational efficiency. Therefore, investing in practical solutions tailored to
address the identified challenges is crucial for PT. Rumah Kreasindo Berkah to
achieve long-term success and sustain its competitive edge.
Through this research, researchers identified
the root cause of the delays at PT. Kreasindo Blessing. The main contributors
to project completion delays are critical factors such as project complexity,
unclear communication flow, excessive approvals, lack of data integration, and
inefficient resource allocation. To overcome these delays, proposed solutions
include implementing a robust inventory management system, training supervisors
and employees, optimising resource allocation, and streamlining production
flows by changing production processes.
By employing the business process modelling
method, the company can identify steps that may lead to delays and determine
the individual responsible for each step. This facilitates a more
straightforward approach to enhancing the production flow or addressing issues
with the specific responsible party. Additionally, the researcher can delve
into the root causes of the problems identified in the preceding business
process analysis through fishbone analysis. Understanding these root causes
simplifies devising effective solutions for the identified issues.
Several steps can be taken as proposed solutions to address the
identified problems. First, ensure precise and agreed-upon client
specifications, criteria, and expectations before commencing the project.
Second, ensure detailed and accurate product specifications and site measurements
in project documentation. Third, adopt a cloud-based data platform for
practical storage and easy accessibility. Fourth, implement a monitoring system
for the availability of crucial products. These recommendations aim to provide
managerial benefits, enhance operational efficiency, mitigate project risks,
and increase client satisfaction. For future research, it is suggested to
explore the impact of delays on customer satisfaction and conduct more in-depth
research on bureaucratic flows aligned with company characteristics. By
implementing these solutions, PT. Rumah Kreasindo Berkah aims to optimise
operational efficiency, reduce project delays, and enhance productivity. These
steps align with the company's strategic objectives, focusing on increasing
efficiency, mitigating project risks, and enhancing competitiveness in the
interior design industry.
Ahmed,
S. (2019). Integrating the DMAIC approach of Lean Six Sigma and the theory of
constraints toward quality improvement in healthcare. Reviews on
Environmental Health, 34(4), 427�434.
Alsharef,
A., Banerjee, S., Uddin, S. M. Jamil, Albert, Alex, & Jaselskis, Edward.
(2021). Early impacts of the COVID-19 pandemic on the United States
construction industry. International Journal of Environmental Research and
Public Health, 18(4), 1559.
Compagnucci,
Ivan, Corradini, Flavio, Fornari, Fabrizio, Re, Barbara, & Tiezzi,
Francesco. (2021). Modelling Notations for IoT-Aware Business Processes: A
Systematic. Business Process Management Workshops: BPM 2020 International
Workshops, Seville, Spain, September 13�18, 2020, Revised Selected Papers, 397,
108. Springer Nature.
Frank, Alejandro Germ�n, Dalenogare, Lucas Santos,
& Ayala, N�stor Fabi�n. (2019). Industry 4.0 technologies:
Implementation patterns in manufacturing companies. International Journal of
Production Economics, 210, 15�26.
Guest,
Greg, Namey, Emily, & Chen, Mario. (2020). A simple method to assess and
report thematic saturation in qualitative research. PloS One, 15(5),
e0232076.
Hasibuan,
Alwi Hamdani. (2022). Materi pendidikan akhlak dalam Tafsir Fi-Zhilalil
Qur�an. IAIN Padangsidimpuan.
Kaid,
Husam, Noman, Mohammed A., Nasr, Emad Abouel, & Alkahtani, Mohammed.
(2016). Six Sigma DMAIC phases application in Y company: a case study. International
Journal of Collaborative Enterprise, 5(3�4), 181�197.
Meredith,
Jack R., Shafer, Scott M., & Mantel Jr, Samuel J. (2017). Project
management: a strategic managerial approach. John Wiley & Sons.
Mundra,
N., & Mishra, Rajesh P. (2023). Developing a model of critical failure
factors for integrated LSS�AM practices in Indian manufacturing industries: a
fuzzy TISM approach. International Journal of System Assurance Engineering
and Management, pp. 1�13.
Parpongpun,
J. (2020). Key factors cause the delay and loss of work in the construction
business.
Rifqi,
Hanane, Zamma, Abdellah, Souda, Souad Ben, & Hansali, Mohamed. (2021). Lean
manufacturing implementation through DMAIC Approach: A case study in the
automotive industry. Quality Innovation Prosperity, 25(2), 54�77.
Rosengart,
Alessandro, Granzotto, Maja, Wierer, Rudi, Pazzaglia, Gianluca, Salvi,
Alessandro, & Dotelli, Giovanni. (2023). The Green Value Engineering
Methodology: A Sustainability-Driven Project Management Tool for Capital
Projects in Process Industry. Sustainability, 15(20), 14827.
Septiawan,
Dimas Budi, & Bekti, Rudy. (2016). Analysis of Project Construction Delay
Using Fishbone Diagram at PT Rekayasa Industri. Journal of Business and
Management, 5(5), 634�650.
Serban,
Ioan, & Marinescu, Corneliu. (2013). Control strategy of three-phase
battery energy storage systems for frequency support in microgrids and with an
uninterrupted supply of local loads. IEEE Transactions on Power Electronics,
29(9), 5010�5020.
Wilson,
A. N., Kumar, A., Jha, A., & Cenkeramaddi, Linga Reddy. (2021). Embedded
sensors, communication technologies, computing platforms and machine learning
for UAVs: A review. IEEE Sensors Journal, 22(3), 1807�1826.